Caltech Submillimeter Observatory Decommissioning Update

Last summer, Caltech began the decommissioning of the Caltech Submillimeter Observatory (CSO) on Maunakea. The removal and restoration of the site is expected to be completed during 2023. A review of what has been accomplished so far and a timeline for the remainder of the decommissioning is described below.

“The decommissioning is a multistep process with many variables,” said Caltech physics professor and CSO director Sunil Golwala. “Delays in preparatory steps and contracting brought the physical deconstruction close to winter when weather conditions impeded work at the summit. Removal of the telescope, physical deconstruction of the building housing the telescope, and restoration of the site are now anticipated to begin when summit weather conditions allow in spring 2023,” said Golwala.

In addition to retaining contractors as previously noted, Caltech has now completed the selection of cultural and invasive species monitors. “All monitors required by the CDUP [Conservation District Use Permit] are under contract now,” said Golwala. Caltech has retained AECOM/SWCA as the invasive species monitor (on-site and for vehicles), ASM Affiliates as the archeological monitor, and TayMade Productions LLC as the cultural monitor.

So far, the following decommissioning steps have been completed:

  • A perimeter fence was constructed by Islandwide Fencing at the site in September to delineate the construction zone. This fence allows the public to view site activity without safety risk.
  • Kona Transportation has removed the bulk of Caltech’s property inside the observatory, packing it for shipment to Chile (where the telescope is being relocated) or transporting to a local scrapyard for reuse, recycling, or disposal. The telescope remains in the dome, along with a handful of large pieces of equipment and optics.
  • Unitek removed loose lead-based paint and mold-contaminated surfaces in September. Lehua Environmental Inc. provided environmental air monitoring and inspection services during the lead paint removal and mold remediation activities to ensure full containment of these materials. The work was done in accord with the Site Decommissioning Plan (SDP).
  • Oasis Environmental and EnviroServices & Training Center inventoried and removed hazardous materials/waste from the observatory in August and October.
  • Isemoto Contracting has been hired to provide crane services at the summit for telescope removal.
  • Caltech has been in close contact with Hawai‘i Department of Transportation, Hawai‘i County Police Department, and County of Hawai‘i Department of Public Works on road permitting requirements for the transport of the telescope to the Kawaihae Harbor. Okahara and Associates has been brought on to prepare traffic control plans and to assist with permit applications. The transportation plan includes a test run. Due to public notice requirements and allowing for unpredictable weather conditions at the summit, the removal process, including the dummy run, will take place over 3-4 weeks in the spring.

The next steps are as follows:

  • Between now and spring, traffic control plans will be finalized and permits obtained to move the telescope; the public will be informed of planned road closures and restrictions (five individual nighttime closures/restrictions and two individual short daytime closures are anticipated).
  • Once weather conditions are suitable, the crane and other equipment needed for removal of telescope will be mobilized and the removal will commence.

Once the telescope is removed, the project will be turned over to Goodfellow Bros., the general contractor, who will handle the dismantling of the buildings that housed the CSO telescope and the full restoration of the site. M3 will provide deconstruction administration services, while AECOM will provide the independent decommissioning construction monitor (IDCM). Caltech anticipates that decommissioning and restoration will be completed during 2023.

The cost of deconstruction and restoration is expected to be more than $4 million.

The deconstruction process is governed by the CDUP, which was issued by the state’s Department of Land and Natural Resources (DLNR) in January 2022. The CDUP sets the terms and conditions that Caltech must follow during the decommissioning. Copies of the CDUP, the Final Environmental Assessment, the SDP, and other planning documents can be found here: http://www.cso.caltech.edu/wiki/cso/outreach/outreach.

The CSO came online in 1987 and was used by scientists at Caltech and other institutions, including almost 200 student and postdoctoral researchers, to open a new submillimeter window on the universe. A summary of CSO’s contributions to astronomy and astronomical instrumentation are available here: http://www.cso.caltech.edu/wiki/cso/science/overview.

Source – Caltech
Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending

Best phones under 20000 in 2026 held in hand Best phones under 20000 in 2026 held in hand
Technology1 week ago

Best Phones Under 20000 in India 2026: Top 7 Picks

Finding the best phones under 20000 in India has never been this rewarding. In 2026, this price band buys a...

A loyal customer receiving coffee, showing brand loyalty A loyal customer receiving coffee, showing brand loyalty
Branding2 weeks ago

Brand Loyalty: How Successful Brands Keep Customers Coming Back

Featured image — Source: Thirdman / Pexels It costs far more to win a new customer than to keep an...

Billboards in a city boosting brand awareness Billboards in a city boosting brand awareness
Branding2 weeks ago

Brand Awareness: Effective Strategies to Grow Your Business

Featured image — Source: Anurag Jamwal / Pexels Before anyone can buy from you, love you, or recommend you, they...

Brand equity represented by the word value Brand equity represented by the word value
Branding2 weeks ago

Brand Equity Explained: Meaning, Importance, and Examples

Featured image — Source: Ann H / Pexels Two bottles of fizzy brown cola sit side by side. One is...

Phone software updates and long-term support in 2026 Phone software updates and long-term support in 2026
Technology2 weeks ago

Best Phones Software Updates in 2026: How Many Years of Support Every Brand Gives

When you buy a phone in 2026, the spec that quietly matters most isn’t the camera or the chip —...

Brand positioning strategy planning on a board Brand positioning strategy planning on a board
Branding2 weeks ago

Brand Positioning: Definition, Strategies, and Real-World Examples

Featured image — Source: Leeloo The First / Pexels Two coffee shops sit on the same street, sell a similar...

Visual representation of brand identity, image, and reputation Visual representation of brand identity, image, and reputation
Branding2 weeks ago

Brand Identity vs Brand Image vs Brand Reputation: Key Differences

Featured image — Source: Eva Bronzini / Pexels Ask ten marketers to explain the difference between brand identity vs brand...

How to build a brand from scratch strategy planning How to build a brand from scratch strategy planning
Branding3 weeks ago

How to Build a Brand From Scratch: A Step-by-Step Guide

Featured image — A brand starts with strategy, not a logo. Source: Walls.io / Pexels Every business you admire started...

What is branding - a complete beginner guide What is branding - a complete beginner guide
Branding3 weeks ago

What Is Branding? A Complete Beginner’s Guide

Ask ten people what branding means and you’ll get ten different answers. Some say it’s your logo. Others point to...

Perfume Brands Perfume Brands
Lifestyle3 weeks ago

Best Perfume Brands in India (2026): Top Luxury & Affordable Fragrances Ranked

Choosing from the best perfume brands in India has never been more exciting — or more confusing. Walk into any...

Translate »